The construction progress of the flue gas desulphurisation plant (FGD) in the lignite power plant Ugljevik is proceeding as planned.
28
Mar
The construction progress of the flue gas desulphurisation plant (FGD) in Ugljevik
Energy Solutions

The construction progress of the flue gas desulphurisation plant (FGD) in the lignite power plant Ugljevik is proceeding as planned.

The flue gas desulphurisation (FGD) project at the Ugljevik thermal power plant in the Republic of Srpska in Bosnia and Herzegovina, which construction began last spring, is well underway. This flue gas desulphurisation project will be the first retrofit of a coal power plant in the Western Balkans to reduce sulfur dioxide and particles in the atmosphere.

Current state of construction:

Absorber

Limestone silos with limestone unloading area

Flue gas duct (from booster fan toward the absorber)

Booster fan