Project Status: FGD Plant at the “Nikola Tesla A” thermal power plant in Obrenovac, Serbia
16
Nov
Energy Solutions Project Managemnet

Project Status: FGD Plant at the “Nikola Tesla A” thermal power plant in Obrenovac, Serbia

 

➡️ Installation of FRP pipelines and recirculation system pump house is progressing well.

➡️ Rubber lining of tanks and the flue gas ducts on C1 are going well, all seventeen segments of the wet stack on the absorber C1 were successfully installed.

Since 2019, Activ has been working on this large and important project together with Mitsubishi Power, Japan.

This project represents a significant environmental contribution to Serbia thanks to the FGD system, emissions of sulphur dioxide and particles will be reduced 9️⃣-times in the future, from about 74,000 tons to 7,800 tons per year.