Trial operation of FGD plant at TPP Ugljevik continued
6
Aug
Energy Solutions Project Managemnet

Trial operation of FGD plant at TPP Ugljevik continued

The company Mitsubishi Hitachi Power Systems (MHPS) withdrew its experts due to the COVID-19 epidemic in April 2020, which partially stopped the trial work. At the end of July 2020, the plant was put into operation again, and the TPP Ugljevik reduced the level of air pollution significantly below the prescribed environmental standards. As of 26 July 2020, the flue gas desulphurisation (FGD) plant in the TPP Ugljevik is back in operation. According to Milutin Tasovac (executive director of TPP Ugljevik), it is showing excellent results, and the trial work will last another 15 days.

Learn more: https://www.youtube.com/watch?time_continue=2&v=BxI54VnSK_Y&feature=emb_logo