Here’s a quick snapshot on our progress of the FGD Plant TENT B project:

🔷 Absorber B2: Sandblasting of the internal surfaces is well underway, covering approx. 2800 square meters! This marks the final stage before gumming, where we anticipate rubberizing around 3800 square meters.

🔷 Second Absorber: We’re wrapping up the preparation of cell surfaces, signaling another significant milestone!

🌍 Environmental Impact: Our dedication to environmental sustainability is unwavering. With the completion of the new desulfurization unit:
– We will reduce SO2 emissions from 80,000 tons annually to a remarkable 4,500 tons — that’s a 20-fold decrease! 📉
– We’re aligning ourselves with the European Union’s Industrial Emissions – Directive (IED) and the new BREF-Best Available Techniques reference docs, aiming for a 96% cut in the plant’s sulfur dioxide emissions. 🌳

➕Stay tuned for more updates on our journey towards a sustainable and environmentally responsible future. 🌱