📢A project status update on the FGD Plant at the Nikola Tesla B Power Plant in Obrenovac, Serbia🚧
Here’s a quick snapshot on our progress of the FGD Plant TENT B project:
đź”· Absorber B2: Sandblasting of the internal surfaces is well underway, covering approx. 2800 square meters! This marks the final stage before gumming, where we anticipate rubberizing around 3800 square meters.
đź”· Second Absorber: We’re wrapping up the preparation of cell surfaces, signaling another significant milestone!
🌍 Environmental Impact: Our dedication to environmental sustainability is unwavering. With the completion of the new desulfurization unit:
– We will reduce SO2 emissions from 80,000 tons annually to a remarkable 4,500 tons — that’s a 20-fold decrease! 📉
– We’re aligning ourselves with the European Union’s Industrial Emissions – Directive (IED) and the new BREF-Best Available Techniques reference docs, aiming for a 96% cut in the plant’s sulfur dioxide emissions. 🌳
➕Stay tuned for more updates on our journey towards a sustainable and environmentally responsible future. 🌱
🤝Together, we can make a difference!