🏭 Project Update on the Phase 2 of the FGD Plant at the “Nikola Tesla A” power plant in Obrenovac, Serbia
👉 The lime slurry made in Phase 1 is propelled to Phase 2 through a pipeline. Phase 2 consists of two absorbers with wet stacks, which purify flue gasses. The byproduct of this purification process is the gypsum suspension, which then embarks on a circular journey back to Phase 1.
📸 Take a look at the progress in the accompanying photos. There you can see our impressive absorbers in action.
🌉 Another key feature is the pipe bridge that carries the pipelines which transport the lime suspension to the absorbers and return the gypsum suspension to Phase 1.
🔧 A major milestone: The flue gas absorber ducts are in their final stages. With all components expertly lifted and welded, the focus has shifted to insulation and panel installations – a display of precise craftsmanship.
✅ We are excited to share that Phase 2 is well underway and is projected to be successfully completed by the end of November.