๐ญ Project Update on the Phase 2 of the FGD Plant at the โNikola Tesla Aโ power plant in Obrenovac, Serbia
๐ The lime slurry made in Phase 1 is propelled to Phase 2 through a pipeline. Phase 2 consists of two absorbers with wet stacks, which purify flue gasses. The byproduct of this purification process is the gypsum suspension, which then embarks on a circular journey back to Phase 1.
๐ธ Take a look at the progress in the accompanying photos. There you can see our impressive absorbers in action.
๐ Another key feature is the pipe bridge that carries the pipelines which transport the lime suspension to the absorbers and return the gypsum suspension to Phase 1.
๐ง A major milestone: The flue gas absorber ducts are in their final stages. With all components expertly lifted and welded, the focus has shifted to insulation and panel installations โ a display of precise craftsmanship.
โ We are excited to share that Phase 2 is well underway and is projected to be successfully completed by the end of November.